The scheme contractors, Ringway, have experienced several issues with access to this site and unforeseen issues under the ground mean that they are running over time on the project. Ringway will be extending the works due to these issues and expect the installation to be completed next week (week commencing the 13th of November). The lighting will not be working until the power connection is made in front of Budgens, Claggy Road until mid December.
When the power is connected, they will test the lighting equipment and the lights will be working that evening.